PITTSFIELD, Mass. – Please be advised of the following work that will take place July 15-19, as part of the City of Pittsfield’s 2019 Street Improvement Project.

During this work, on-street parking will be prohibited in the locations mentioned below, with the exception of the streets identified for work on July 18-19. The schedule is as follows:

Monday, July 15 and Tuesday, July 16: Installation of curbing on Stoddard Avenue and Myrtle Street.

Wednesday, July 17: Installation of curbing on Pontoosuc Avenue.

Thursday, July 18 and Friday, July 19: Loam and seed placement on Stoddard and Glenwood avenues and Pine, Myrtle, and Grove streets. Please note on-street parking is permitted.

Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.