In a press release from The City of Pittsfield, due to inclement weather, please be advised of the following updates to the City of Pittsfield’s 2019 Street Improvement Project through June 28.

During this work, on-street parking will be prohibited in all of the locations mentioned below. The schedule is as follows:

Wednesday, June 19: Mill existing pavement on Hull Avenue, Myrtle Street, and Stoddard Avenue.

Thursday, June 20: Mill existing pavement on Pontoosuc Avenue and Brighton Avenue.

Friday June 21: Mill existing pavement on Somerset Avenue and Windsor Avenue.

Monday, June 24: Paving-shim course on Grove, Glenwood, Pine Street, and Pleasure Avenue.

Tuesday, June 25: Paving-shim course on Myrtle Street, Stoddard Avenue, and Hull Avenue.

Wednesday, June 26: Paving-shim course on Pontoosuc Avenue and Brighton Avenue

Thursday, June 27: Paving-shim course on Somerset Avenue and Windsor Avenue.

Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.